Date Completed: December 2005
Project Description:
The Tundish Tilting station (50 T Capacity) was designed
to empty tundishes of the cooling metal, slag, and deposits
that remain after the continuous casting process. In
order for tundishes to be re-lined and cycled back into
production it is critical that all these remaining materials
be removed. The process of dumping, shaking, or punching
tundishes to rid them of “skull” material
build-up occurs at the tundish tilting station.
Characteristics:
- Max. load of the tundish including remaining metal
allowable for tilting is 50 T
- Installed Current/Power: 30kw regulating frequency
- Working Hydraulic Pressure: 160 bar
- Hydraulic Motor Power: 7.5 kw
- Maximum # of Rotations: 1.5o/min
- Degree of Platform Rotation: 180°
- Degree of Platform Sway: +- 10°
Project Phases:
- Detailed Civil, Electrical, and Mechanical Design
- Assembly and Construction
- Equipment specification and procurement
- Ordering of controls and control Pulpit
- Programming PLC / Control logic
- QA during manufacturing
- Start-up during Commissioning
- Shop Testing
- Training of Production and Maintenance Personnel

|